How to change the Activity ID of a group of activities?

Pranab Kumar DebMember for 19 years 8 months
Created
7
3
0
Dear All ,
How to change the activity ID of a group of activities in faster manner and not by manually for all the activities.
I tried with import/export but the problem is that the activities where i change the activity ids comes in as new acivities.
Please advice.
regards
deb

7 replies

Oldest first
  1. 0
    Ferdinand U. ·
    try global change using the &T1 function &..
  2. 0
    Pranab Kumar Deb ·
    Hello Ferdinand,
    Thanks for your reply can please elaborate how to use this function.
    regards
    deb
  3. 0
    Dattatreya Padharthi ·
    Pranab,

    Use the Global Change; if you want to change a charecter/s in the middle, extract all charecters before that lot and also extract all charecters after that lot and save as a temporary variable. then use the concatenate function.
    Cheers
    Dattatreya
  4. 0
    Pranab Kumar Deb ·
    Hello Ferdinand and Dattatreya ,
    can you please list in more details the procedure.
    regards
    deb
  5. 0
    Ferdinand U. ·
    example change A100000000 to B200000000

    global change

    if ACT CN A1
    then ACT EQ B2 & right(ACT,8)

    run
  6. 0
    Daniel Limson ·
    There is another way of doing it by copy and paste. Select auto increment and delete the ones you want to change. The only problem here is you will loose the relationship outside of the group you copied and pasted.

    Cheers
    Daniel
  7. 0
    Pranab Kumar Deb ·
    thanks daniel , ferdinand and dattareya
    it was a great help
    regards
    deb