Export P3 file to Excel and import Excel to P3

Amit AmitMember for 20 years 2 months
Created
1
13
0
Hi,

How do i Export a P3 file to Excel and then import the updated excel file back into P3.

1 reply

Oldest first
  1. 0
    Dattatreya Padharthi ·
    Amit,
    If you are using Office 2003,Export as *.dbf file , open in excel modify, save as dbf with errors.
    Import back in P3.(Check for number of activities during this process.
    If using Office 2007, export as dbf, open in MS access, modify/change & save as dbf & import back.

    Cheers
    Dattatreya