duration calculation in p3& p5
In the Open Standard
Mangesh KhuspeMember for 19 years 6 months
- Created
- 2
- 1
0
hi
i had to export some progs in p3 for but when i looked at the durations in p3 it had changed
Let me explain in p5
say activity A start date & finish dates are
02/05/07 , 05/08/07.
but same activity A in p3 has start & finish dates
are 02/05/07, 02/08/07.
Calender is same in both,
the relationship remains the same.
then why does it calculate like that?
cheers
mangesh
i had to export some progs in p3 for but when i looked at the durations in p3 it had changed
Let me explain in p5
say activity A start date & finish dates are
02/05/07 , 05/08/07.
but same activity A in p3 has start & finish dates
are 02/05/07, 02/08/07.
Calender is same in both,
the relationship remains the same.
then why does it calculate like that?
cheers
mangesh
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?