duration calculation in p3& p5

Mangesh KhuspeMember for 19 years 6 months
Created
2
1
0
hi
i had to export some progs in p3 for but when i looked at the durations in p3 it had changed
Let me explain in p5
say activity A start date & finish dates are
02/05/07 , 05/08/07.
but same activity A in p3 has start & finish dates
are 02/05/07, 02/08/07.
Calender is same in both,
the relationship remains the same.

then why does it calculate like that?

cheers
mangesh

2 replies

Oldest first
  1. 0
    John Raper ·
    Mangesh

    This is only a guess but check it out.
    I assume your ’planning unit’ in P3 is ’Days’. In P5 the planning unit is always hours, but appears as days. You will need to check the hours/day in ’Admin|Admin Preferences|Time Periods’. This deterimnes the calculation for hours per day etc.
    You may need to change the duration, then change it back, for the duration to be re-calculated.

    Hope this helps.
  2. 0
    Mangesh Khuspe ·
    hi
    John

    Thanks for your help it solved my problem.

    Thanks PP


    Cheers

    Mangesh