Estimated Duration
In the Open Standard
MA
Moutaz AldeibMember for 22 years 9 months
- Created
- 23
- 4
0
23 replies
Oldest first- 0RWRonald Winter ·Presumably, the contractor was hired because he or she is an expert in building the desired product. If there is no written historical data, then surely there is a resident expert who can estimate the task duration. If you lack such an expert, one wonders why you ever bid to perform such work. Good luck!
- 0MTMike Testro ·Hi Moutaz
The most usual way is by personal experience and guesswork.
This works better if you have to make a lot of guesses rather that one big one.
If you have a cost plan or BOQ you can ascertain resource hours by use of labour percentages for each trade.
These will range from 15% to 55% after adjustment for OH&P.
You will also need to know the hourly labour rate to convert the money to hours.
With the application of a suitable Gang Size and the work hours per day you can estimate the duration in days fairly accurately.
Best regards
Mike Testro - 0MTMike Testro ·Hi Moutaz
1. OH&P means Overheads and Profit.
If the percentage is - say - 15% then the arrithmetic is that 15% is added to the net figure - so if you just deduct 15% from the gross figure you will get a lower number. Use Gross/(1+OH&P%) to get the net total.
2. No - you have to convert the labour % in money to labour hours by dividing by the labour rate.
The percentage band differs by the ratio of plant and material to labour so for instance:
Fix Chrome Tap - Rate = $20 - Lab % about 30%
Fix Gold Plated Tap - Rate = $200 Lab % about 10%
You will have to apply experience and common sense to get the percenatges right and it is better to apply it to BOQ section summaries rather than individual items.
Best regards
Mike Testto - 0WSWaseem Saber ·Samer,
working 10th time (repeated) will take less time than the 9th time etc.... provided you have the same resources and no change in hand has taken place, i have noticed that more often then not when the resources change hands the productivity take the dips, the repeat fuction helps when all the enviornment and the labour and plant is remained the same.
hope this will kick start some good discussion on this aspect
cheers
Wazsab - 0MTMike Testro ·Hi Moutaz
There are a number of publishers of estimating software that use industry standard output rates that can be adopted for resource modelling.
Care must be taken that the work description is the same as that in your project.
I use Wessex Estimating - which is now published by the RICS on a set of discs.
Hutchinsons is used a lot.
They are not cheap.
I would avoid the PP rates as there is no audit trail to the source and don’t even bother with wikipedia.
Best regards
Mike Testro - 0MTMike Testro ·Hi David
I often have to put together resource modelled programmes based on BoQ rates that are just extracts from sub-contractor’s prices.
No unit breakdown into Lab Plant Mat or OH&P.
If the budget allows I run the BoQ through Wessex software otherwise I use the labour percentage method.
Very few UK construction firms prepare estimates from historical data and none that I have come across keep production records on current projects.
Best regards
Mike Testro - 0AIAnoon Iimos ·Hi Moutaz,
How are you? I believe you know how to do it, and of course you got all the productivity rates with you (just go to the library) but just in case you might ask me,: Productivity depends on the resources or the type of resources being used.
For example: Excavation, first you may define what type of soil it is, or is it a rock? For sure there is a soil analysis from your engineering dept. And are you going to use machines (excavators)? or just manual?
But don’t worry, we are doing your project.
Best regards - 0SZSamer Zawaydeh ·Dear Patrick,
The first thing that you must do is creat an activity list. Try to use and active verb and a noun for each activity.
Planning is a group work. You invite the people responsible for completing these activities and ask them how much time they need to complete them. They are the best source of information.
With kind regards,
Samer - 0SDSe de Leon ·It’s kind of hard to say that what your supervisors has given you has too much float or in other case, aggressive. You really have to demonstrate to them that what they gave you is unrealistic. You can only do this if you have the right experience to convince them.
If you follow certain norms or standards, they may say you’re being bookish and unrealistic.
If you don’t have the experience, ask a 2nd expert’s opinion or maybe 3rd. Pretty much after that, you can have a guage of what is realistic or not.
My 2 cents. - 0SZSamer Zawaydeh ·Dear Patrick,
Software is a tool. Garbage in Garbage out.
You need to make sure that the list is correct, the sequence is correct and the durations are as per the users requests. Then you start the development and trial and error. Give your team members what you get the first time, and let them correct their rates of production and duration. This way the Program will be realistic.
With kind regards,
Samer