Percentage Progress

Divya BhardwajMember for 19 years
Created
10
4
0
Hi all!!!
I am very new to tghis site as well as the Planning field. Can you all help me by telling "how to find out the monthly % progress for whole project". My project started in February and now I have to give the planned % progress till 2009.
Thanks
Divya

10 replies

Oldest first
  1. 0
    Anoon Iimos ·
    calculate the planned values from your Target Schedule
  2. 0
    Karim Mounir ·
    Hi Divya,

    U have to use the same method which u’ll be using to get your actual progress % (ie. compare apple to apple).
    For example: manhours, cost, activity days, etc..
    U measure ur planned figures using ur target sch.

    Regards,
    Karim
  3. 0
    A D ·
    If ur program is not resource loaded, then you can use duration as resource and then can find the monthly progress.

    Assign a resource = R to all activities and then thro global change assign BQ=OD

    Go to Tabular reports and get ur monthly figures.

    Hope I am clear.

    Cheers,

    Ravi
  4. 0
    Divya Bhardwaj ·
    I am afraid I am not. I am new to all this so dnt know the meanings of BQ=OD
  5. 0
    Karim Mounir ·
    BQ: Budgeted Quantity
    OD: Original Duration

    After assigning the "R" resource to all activities, do the following:
    Access the global change through Tools -> Global Change
    1- Click on "Add", name it..
    2- In the "Change" tab, In the "Then" statement type, under Data item right click and select "BQ".
    3- In the "Then" statement type, under Criteria right click and select "EQ".
    4- In the "Then" statement type, under Data Item/Value right click and select "OD".
    5- In the "Selection" tab, under "Select if" right click and select "Resource", under "Is" right click and select "EQ", under "Low Value" right click and select "R".

    Regards,
    Karim
  6. 0
    Edderic See ·
    Hi all,

    Karim, I think schedule progress is good for estimation purpose only but if it is use for actual work i think you should cost load it with major resources. That way, it is more accurate in a long run.

    Regards,

    Ed
  7. 0
    Karim Mounir ·
    Yes Ed but to load every activity in the sch. with cost u need to have accurate estimates (ie. get detailed quantities from the QS).
    This is not avaliable every time.

    Usually we use this "Activity days" method for weightage purpose only.
  8. 0
    Edderic See ·
    Hi Karim,

    I totally agree with you. When i was a site planner, i need data from our qs so that our project manager knows the cost requirement every month. That is the only way, a tedious but prudent measure for the good of the project. When i became a tender planner, i also use your method because first, it is a typically a 5 min work and lastly, it is only a bid project.

    Regards,

    Ed
  9. 0
    A D ·
    Hi Edd,

    If u r very much conversant with P3, yes then off course u can resource load the program, give appropriate weightage and then check the monthly % progress.

    As Divya is new to the entire system, to start with it would advisable for him to calculate the % progress in terms of OD as suggested. Later on, he can resource load it and can get closer to the factual basis.

    :-)

    Rav
  10. 0
    Divya Bhardwaj ·
    hi All
    Well Thaks a lot for all your replies. It helped me a lot.
    Thanks again.
    I had also posted query for % progress last week,, can u all help me in that too?