Suretrak progress query
In the Open Standard
Wasi RazaMember for 21 years 5 months
- Created
- 2
- 1
0
I have just started working on suretrak again after quite a while. this query relates to progressing an activity to data date 23-sep-07
Activity details
OD - 20 days
progressed 50% to 23-sep-07 with actual start 25-jul-07
rem dur calculated as 10 days
now when i shedule the project to data date the activity runs all the way to 2-nov. logically it should just extend to 5-oct considering 10 days after data date. i cannot see any reason why it should when there are no finish to finish links on the activity at all.
Any body?
Activity details
OD - 20 days
progressed 50% to 23-sep-07 with actual start 25-jul-07
rem dur calculated as 10 days
now when i shedule the project to data date the activity runs all the way to 2-nov. logically it should just extend to 5-oct considering 10 days after data date. i cannot see any reason why it should when there are no finish to finish links on the activity at all.
Any body?
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?