problem with histogram
In the Open Standard
Artur CorreaMember for 18 years 11 months
- Created
- 2
- 2
0
I am working with Primavera 5.0. I have several construction sites which start and finish at different time. I would like to know how many supervisors (one per site) I will need, example: in April four construction sites will start so it’s mean that I need 4 supervisors. I would like to see it on the histogram. Every time when I assign resources or roles I receive hours per month. What should I do?
2 replies
Oldest firstLog in or join to reply