Adjust Working Hours
In the Open Standard
Karim MounirMember for 20 years 6 months
- Created
- 2
- 3
0
Hi,
When I exported the P3 sch to P5, I got 1 day difference in the early finish of the latest activity in P5.
I consulted the Primavera rep. and he notified me that this is a bug in P5 which they solved in P6.
Is this true?, can I adjust the working hours in P3 to be the same as in P5 (ie. 10 working hours/day) and if so will this solve this issue?
Regards,
Karim
When I exported the P3 sch to P5, I got 1 day difference in the early finish of the latest activity in P5.
I consulted the Primavera rep. and he notified me that this is a bug in P5 which they solved in P6.
Is this true?, can I adjust the working hours in P3 to be the same as in P5 (ie. 10 working hours/day) and if so will this solve this issue?
Regards,
Karim
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?