Adjust Working Hours

Karim MounirMember for 20 years 6 months
Created
2
3
0
Hi,

When I exported the P3 sch to P5, I got 1 day difference in the early finish of the latest activity in P5.
I consulted the Primavera rep. and he notified me that this is a bug in P5 which they solved in P6.

Is this true?, can I adjust the working hours in P3 to be the same as in P5 (ie. 10 working hours/day) and if so will this solve this issue?

Regards,
Karim

2 replies

Oldest first
  1. 0
    Johny Kesserwany ·
    Hi Karim,

    P3 is based on working days and not on hours. P5 & P6 are hours based and any schedule converted from P3 will have the same problem. P6 too has the same bug.

    Regards
    JK
  2. 0
    Karim Mounir ·
    Thanks JK