Total Project Manhours/mandays

Jeev RajMember for 23 years
Created
6
6
0
In Primavera Project Planner which is the best way to know total manhours/mandays on the project

6 replies

Oldest first
  1. 0
    Gilbert Rayco ·
    Dear Jeev,

    IMHO For quick report:
    - tools, tabular reports, matrix, resource/cost
    or
    - tools, tabular reports, resource, tabular

    Hope this will help

    G. Rayco
  2. 0
    Mk Tse ·
    No report until you have assigned human resources to activities.
  3. 0
    Jeev Raj ·
    Gilbert,

    Thanks for your response. I will work on this approach and also see if same can be applied for individual equipments too.

    Jeev
  4. 0
    Gilbert Rayco ·
    Dear Jeev,

    I’m confident that it can be done as long as u identify
    individual equipment in ur resource library.

    Good day,

    G. Rayco
  5. 0
    Jorge Taguinod ·
    You may also want to use cost categories (e.g. L-Labor, M-Material, E-Equipment, etc.) If you do this, then you could simply organize by cost categories and summarize to get your totals.

    Hope this helps.

    Jorge
  6. 0
    Zq qz ·
    You can also do it using report writer.

Log in or join to reply