Level 4 Schedule example

Gie Chris RimandoMember for 19 years 8 months
Created
1
1
0
Hi to all!

Can somebody send me an example of a LEVEL 4 schedule..

We have a running projects at the moment.Our client required us to submmit a level 4 schedule from our current running schedule, for them to specifically determine the problem area of our project,since we are running late already due to a lot of delays.I haven’t made such one before and i just want to see how detailed a level 4 is.

Our project is a building addition.

My e-mail add is azalea_0301@yahoo.com


Thanks for the help in advance.

1 reply

Oldest first
  1. 0
    James Barnes ·
    I’m not sure if there’s a standard approach to numbering or describing levels of detail, but we use;

    Level 1; Top level milestones - 1 A4 sheet for the project
    Level 2; Phase level planning - 1 A4/A3 sheet per work area - Gives focus to phase lengths (planning, execution etc)
    Level 3; Execution strategy - a few A4/A3 sheets per work area - details overall approach to the execution of the works
    Level 4; Activity detail - 20k+ activities - 1 activity per man-shift
    Level 5; MH calculation lines that drive the activities

    This is used for Oil and Gas maintainence turnarounds, traditional building work I would say may lack level 5 completely and be of the order of one man-month per activity at level 4 (depends on your reporting period.)

    I expect, though, that what your employer is demanding is one level of detail deeper than whatever you are currently providing. It is a common technique to scheudule the next 2-4 months work in a deeper level of detail than your overall plan, in your case perhaps you start the project with a level 3 plan for the whole project before you start (at tender perhaps) and then to schedule at Level 4 the works coming in the next 3 months. The term for this is "rolling wave" planning

Log in or join to reply