Skip to content

Calculating the progress using P3.1

MOHAMED nizarMember for 18 years 9 months
Created
8
5
0
Hi,
Which one is more acurete duration, cost or resources to calculate the progress persentage in p3

8 replies

Oldest first
  1. 0
    Alireza Hosseinzadeh ·
    it depend to the scope of your project ;
    if u want to calculate project for procurement , u should use cost of materials / equepment ,... and for engineering and construction the man/hour or quantity are practical. ( please be inform that for some of activities both of items will used )
  2. 0
    Alireza Hosseinzadeh ·
    it depend to the scope of your project ;
    if u want to calculate project for procurement , u should use cost of materials / equepment ,... and for engineering and construction the man/hour or quantity are practical. ( please be inform that for some of activities both of items will used )
  3. 0
    James Barnes ·
    Cost is a result of resource use. Effectively it will weight the resources buy their cost per unit, making progress in more expensive items stand out more

    thus, if you have been able to apply a cost to each of your resource use rates then cost should be the better measure.

    I say should. In fact, we use resource hours without costs to track progress and we track it resource by resource as well as work area by work area and (often) work type by work type. Otherwise it can be easy to think that you are "on time" because you are ahead on an expensive item but behind on several cheap ones.

    In the end. Cost is better but you need to have an eye on progress from seevral angles, not just overall or you can lose sight of the detail.
  4. 0
    Nar Thap ·
    OK percentage complete can be taken by any otf the method, cost and /or MH, Has anybody any idea how to show summerised percentage completion of whole project at the top of the column if you are using cost /MH as measure of progress? OR how do you show overall project progress of a EPC?
  5. 0
    Jim McCombs ·
    Actually, your question "Which one is more accurate: duration, cost, or resources to calculate the progress percentage in p3" is somewhat vague. Are you asking on an activity basis or project overall basis for percent complete? And, the answer depends upon what is it you are measuring: cost, resources, or time. Mostly, I use schedules as a time management tool and thus, I am more interested in time. So, I am not really interested in percent complete, but rather I want to know how long will it take to finish, i.e. remaining duration. So, what is it you are really wanting to know?
  6. 0
    Anoon Iimos ·
    I guess everybody wants to know if how much profit they’ll get if they finish ahead of schedule. So it is always a combination of Time and Money.
  7. 0
    MOHAMED nizar ·
    Dear Mr. James,

    When I calculate the overall project percentage using these three tools cost, resources and duration I get three different values. This is my problem. Which one can I assume as the acurate percentage completed. Pl help me.
  8. 0
    Alexandre Faulx-Briole ·
    Mohammed,
    in a very simple schedule with all activities on a line, you will have percentage for actual duration, actual work and actual cost the same;
    but a project is not often as simple: imagine you have 2 or 3 activities occuring at the same time, the actual work % will be above the actual duration %
    on the contrary, if you have large lags between activities, the actual duration % will be above the actual work %
    I hope this helps
    Alexandre

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?