MS Excel & Importing into SureTrak

Shane PouchMember for 18 years 8 months
Created
1
1
0
Hello,

I am new to this forum. Have used P3, SureTrak, and MSProject off and on over the 20 years I’ve been in the construction industry.

I am currently using SureTrak 3.0b version 2, and my issue right now is with using MS Excel and trying to import activities back into SureTrak.

I am tryint to use the Copy Activity function to first copy to MS Excel so that all the columns are established. Then I simply work in MS Excel to make my additions/changes, etc. Then I highlight the data in the spreadsheet and copy it. Then I go back into SureTrak and position the cursor at the activity where I want to insert my activities and use the Paste Activity function.

Here’s where the problem comes in. Why don’t the predeccessors/successors show up?

Any help will be greatly welcomed and appreciated.
Thanks,
Shane

1 reply

Oldest first
  1. 0
    Ernesto Puyana ·
    I’ve used the exact procedure you describe, to import resource assignments, but once i tried to import predecessors, what i got was a duplicate FS relation for each activitiy.

    By the way, have you tried using the pivot table. I’m getting an illegal function message every way i try it. Can you help me?

Log in or join to reply