hi,
I am new to planning and I would like to increase MHRS through by Global change.
for exp: my previous MHRS is 1.7 M manhours and now is 2.01 M.
Please can somebody teach me the way of increase of manhours through by Global change.
I am waiting for urgent response from somebody.

1 reply

Oldest first
  1. 0
    Ronald Romero ·
    Use the if then statement to increase the OD or the original duration by a factor that you want for example

    if RESP EQ HARRIS
    then OD EQ OD * 2
    else OD EQ OD *1.5

    Here if the condition that responsibility is by Harris the Original Duration is increase by 200% if not which is the rest it is only 150 %.

    Study also the difference between an AND and OR in boolean algebra since an AND statement only is true when ALL conditions are met while in an OR statement is true if ANY one of the conditions is met or true.

    Regards,