a wrong message on p3 ( tell me please )

Alireza HosseinzadehMember for 18 years 9 months
Created
3
1
0
could anybody explain me about this wrong message that p3 show in my project during of rescheduling and reporting.

" project environment variable is too long "

so thanks

3 replies

Oldest first
  1. 0
    A D ·
    Ali,

    The total path length (wherein u save ur files) must be less than 64 characters.

    Just move your file or shorten your folder name.

    Cheers,

    Ravi
  2. 0
    Ronald Romero ·
    Alizeza,

    The folder location where you save your project is very long already eg. C:\Documents and Settings\administrator.PP-WEB\Desktop\Update\Target\TR02 is more than the project environment variable can handle. I think limited only to 32 characters or bits because its an old software. Today you can name your path to more than 256 or more.

    To solve it copy your folder in a different path say make a folder in drive c:\schedule

    Regards
  3. 0
    venkatesh K ·
    Thanks Ravi & Ronald

    because i can understand the different between those.