Current schedule V/S Target
In the Open Standard
Aloke lalMember for 18 years 7 months
- Created
- 3
- 2
0
I am trying to track progress of a bunch of activities. When I enter the activities which are 100% complete by actuals it is working. Now, when I have some activities that are in the middle i.e 40% complete and when I enter the percent complete and schedule it, the target bars along with the target dates are moving along with the actual. But it shouldnt do this. It needs to fix the target in place and only move the actuals. So i am not able to understand if some of my settings are wrong or for that matter whats the problem.
i would appreciate if anyone can help me fix this.
i would appreciate if anyone can help me fix this.
3 replies