Assigning Resource to Hammock Activity?
In the Open Standard
Pranab Kumar DebMember for 19 years 8 months
- Created
- 6
- 1
0
Dear All,
I want to assign a hammock activity to cover the site cleaning activity from the start of the project to the end of the project.
I have already done this, but now i want to load it with a resource - Unskilled labor for cleaning of the site and assign 100 units( hours ) each day. This i want to do
for working days only , now my problem is that when i assign this resource and put 100 units per day and schedule it it doesnt give me the actual spent till date( considering my project started in Feb 2007.
Moreover the total budgeted quantity field is also not automatically filled & and once i put the actual start date as 1st feb 07 and schedule it on todays date the percent complete field as well is not coming.
Please advise what is wrong , or if you have any better idea of doing this.
regards
Deb
I want to assign a hammock activity to cover the site cleaning activity from the start of the project to the end of the project.
I have already done this, but now i want to load it with a resource - Unskilled labor for cleaning of the site and assign 100 units( hours ) each day. This i want to do
for working days only , now my problem is that when i assign this resource and put 100 units per day and schedule it it doesnt give me the actual spent till date( considering my project started in Feb 2007.
Moreover the total budgeted quantity field is also not automatically filled & and once i put the actual start date as 1st feb 07 and schedule it on todays date the percent complete field as well is not coming.
Please advise what is wrong , or if you have any better idea of doing this.
regards
Deb
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?