RESOURCE PLANNING

Shrikant DesaiMember for 18 years 6 months
Created
1
1
0
Dear Sir,

Kindly let me how enter resource allocation in primevera project planning tool

regards

shrikant

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Shrikant,
    a) create resources in Data, Resources
    b) open the activity form at the bottom of the scree, then click the RES button to open the Resource sub-form
    c) select the 1st activity to which assign a ressource
    d) click in the 1st avaliable column in the RES sub-form, select the resource from the drop-down list, enter either Budgeted Quantity or Units per Day
    ....
    Regards,
    Alexandre

Log in or join to reply