Driving activity in Primavera v 5.0

Arun KumarMember for 18 years 6 months
Created
2
1
0
hi ..


Can anyone tell why P v5.0 in not showing( * ) for dominating link like in P3???


2 replies

Oldest first
  1. 0
    Omar Grant ·
    Hi Arun, you have to select this as a column in the predecessor dialogue box. Right click on the column headings section of the box,select general, then you will see a choice ’driving’. Select this and you will see it in the predecessor dialogue box.
  2. 0
    Arun Kumar ·
    Thanx Omar..Its working.