Dear Planners,

I created time schedule (baseline), but when I draw S-Curve, it was not the common shape, in the midle of the curve the early and late are the same (critical) and then it takes the normal shape, could this be happened? if not, I know there is something wrong with the relationships, how to solve it?

Regards,

Moutaz

1 reply

Oldest first
  1. 0
    Pranab Kumar Deb ·
    Hello Moutaz,
    It can happen only if you have put contrained Finish date.
    In that case you will have negative Total float and hence both can be same or in some cases the late curve may finish early then early curve.
    HTH
    Deb