Placing a line milestone in P3

Smithie JohnnyMember for 18 years 5 months
Created
3
1
0
Help.

I want to show a line milestone in P3. Essentially instead of have a milestone, i would like to plave a line in the schedule that is constrainted by either a date or and activity, so that when i’m scrolling down the page (and for print outs) i can see which activites are before this line and which are after it.

Please help.

Regards
J

3 replies

Oldest first
  1. 0
    Smithie Johnny ·
    Or is there some way of placing a visual aid in the bar chart to show activities before and after this date?
  2. 0
    Smithie Johnny ·
    So i have been told to use the "Line Tool" under the "Attachment Tools".

    It works well, apart from the fact you can only link it to a date and not an Activity.

    Also is there a way to format this Line, so that it stands out more???

    Help???

  3. 0
    Christopher (Chris) Carson ·
    Instead of using the line tool, use the curtain tool (on the same toolbar) and you can set the width so it stands out more. You can also set it to start at a certain date and end at a certain date to bracket your period of review.

    Other than these, you have to go to inserting objects.

Log in or join to reply