SDEF CONVERSION

Zubair UsmaniMember for 21 years 4 months
Created
1
1
0
Does anybody have exp on sdef conversion of p3.
well when i generate sdef file,cost data for some activties do not go very accurate to sdef file.there is a difference in 2digit in decimal.
can anybody help me.

1 reply

Oldest first
  1. 0
    Benjamin Mora ·
    Nothing can be done about the rounding after and before the decimal; short of editing the SDEF .txt file prior to importation. You will have to correct the dollar amounts in QCS\RMS (I assume that you have a NAVFAC, USACOE or AFCESA). Try using whole numbers on your activites, if your contract is a round number; otherwise, you are SOL.