Earned Value and Duration % Complete

Dean MulliganMember for 19 years 7 months
Created
1
1
0
on my project the guys are trying to get the programme cost loaded to meet the clients requirements regarding EV. And are having trouble, mostly due to a disconnect between the cost breakdown and the WBS - costs are at a high level only - thats their problem!

What my problem is that the % Complete used is Duration % Complete.

I have only used Physical % Complete before for EV analysis, is it possible to use Duration % Complete ????

Does Primavera V5 calculate it and does it roll up properly???


cheers

deano

1 reply

Oldest first
  1. 0
    David Kelly ·
    There is no distinction between using either Physical % or Duration % complete in order to set Performance % complete (which is how P5 calculates Earned Value)

    Duration % complete DOES roll up "properly" - but I cannot imagine what you would use that for if the client understands EVA - why not just roll up Performance % complete?

Log in or join to reply