Hi there guys....once again your help please.

I have resourced an activity with 2 resources, quantity and and machine hours. I have created two columns in the custom data (resource) to actually show these two different resources in their respective colums. I am using globle change to populate these columns along side their respective activities....I am getting the summation of the two resources in each of the columns...how do I seperate this data to their respective columns?...please chaps. Thanks

1 reply

Oldest first
  1. 0
    Mimoune Djouallah ·
    hi

    try something like this in global change ( you need to make two global change ) ( quant, and manh are ressources CDI )

    if res EQ quantity

    then quant = (insert your value here)


    and in another global change

    if res EQ manhour

    then Manh = (insert your value here)

    i tried it for one activity and worked as expected

    HTH