Percent complete on P6

Ahmad saeedMember for 18 years 3 months
Created
2
1
0
How can i show the physica % complete for the summarized bars.

2 replies

Oldest first
  1. 0
    Riyadh Yahia ·
    Hi Ahmad,

    physical % complete doesnot roll up through the WBS levels, Try to use performance % complete which will roll up through WBS levels to the project level .

    regards

    Riad
  2. 0
    Ahmad saeed ·
    thanks Riad for replying.

    I tried performance % and it is showing 0% on the WBS level and 100% on the project level.

    thanks
    A