Cost Loading Issues Pls Pls Help
In the Open Standard
Pat GaughanMember for 18 years 3 months
- Created
- 2
- 3
0
Hi I am at my wits end with attempting to cost load activity bars correctly I have tried everything.
I am simply wanting to assign an amount of money to an activity, then when this activity is updated for it to update the spend & remaining budget accordingly.
e.g. if I have an activity which is 10 days long and has £10k assigned to it, if this activity were 3 days (30%) complete I want it to then show £3k spent with £7k remaining. I have created a resource called £ and can get it to show the original amount but as soon as I move the start date, or update the durations, % complete etc it amends the figures & gives me random figures linked to the units per day etc etc
Can anyone help as at the moment I am manually working the figures out & each time I move the data date recalculating the spend & remaining!!
Thanks
I am simply wanting to assign an amount of money to an activity, then when this activity is updated for it to update the spend & remaining budget accordingly.
e.g. if I have an activity which is 10 days long and has £10k assigned to it, if this activity were 3 days (30%) complete I want it to then show £3k spent with £7k remaining. I have created a resource called £ and can get it to show the original amount but as soon as I move the start date, or update the durations, % complete etc it amends the figures & gives me random figures linked to the units per day etc etc
Can anyone help as at the moment I am manually working the figures out & each time I move the data date recalculating the spend & remaining!!
Thanks
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?