Progress Import & Actual Duration

Ife OlykeMember for 19 years 8 months
Created
3
1
0
Guys,

Sometimes when I import progress into P3 say in the order below;

Activity Id Percentage Actual Start ActualFinish
AB1000 100% 23/07/08 23/07/08


P3 stores the Actual start and finish dates in the order below;

Actual Start Actual Finish
23JUL08 00:00A 22JUL08 23:59A

Hence making the actual duration 0; has anyone faced this challenge before? Please share how you dealt with it... Thanks...

3 replies

Oldest first
  1. 0
    Ife Olyke ·
    I just realised it didn’t post properly;

    Sometimes when I import progress into P3 say in the order below;

    Activity Id = AB1000
    Percentage = 100%
    Actual Start = 23/07/08
    Actual Finish = 23/07/08


    P3 stores the Actual start and finish dates in the order below;

    Actual Start = 23JUL08 00:00A
    Actual Finish = 22JUL08 23:59A


    Hence making the actual duration 0; has anyone faced this challenge before? Please share how you dealt with it... Thanks...
  2. 0
    Warren Tolentino ·
    Bro;

    Just please check your calendar. You are in days duration that is why when you put your actual start same as finish the duration will of course be 0. Please remember that your activity is a task type, so it needs a duration to show.
  3. 0
    Ife Olyke ·
    planning unit is in hours and not days... thanks for pointing that out, cos i forgot to mention it earlier...