Global change

Alexandre Faulx-BrioleMember for 23 years 8 months
Created
5
1
0
Hello Planners,
I am going to use Global change to make tasks shorter by a) reducing the BQ, b)making the assigned resource "driving"
I have found the Resource Driving Flag (RDRV) argument in the Global Change list; but I cannot find how to use it: I have tried RDRV EQ "YES", "Y", "1", "T", with no success
Please help,
Alexandre

5 replies

Oldest first
  1. 0
    Joao Ribeiro ·
    Use " " or "*" for non resource driving, resource driving with EQ or NE.

    HTH
  2. 0
    Alexandre Faulx-Briole ·
    Joao,
    Thanks for answering my post
    Maybe I was not clear enough
    Is it posisble to change the "Driving resource" check box in the Activity Details Resource window by using the "Then" section in Global Change
    e.g.
    If ACT EQ 1234
    then RDRV EQ YES
    and RES EQ XYZ
    Thanks for your help,
    Gracias por ayudar me
  3. 0
    Joao Ribeiro ·
    Yes, I think the answer is:

    then RES EQ(AD) XYZ
    and RDRV EQ "*"

    Using it to turn all selected resources into driving. Or, perhaps, using two steps:
    - First, changing the resources
    - Second ,converting then to driving.

    It is also advisable to use "Trial Run" first, just in case...

    Good luck

    Bonne chance.
  4. 0
    Alexandre Faulx-Briole ·
    Joao,
    it works, it works!
    Muchas gracias, hombre
  5. 0
    Joao Ribeiro ·
    Glad to be of help.