Reviewing a schedule

Nadim AkhtarMember for 22 years
Created
5
2
0
I have just joined a Consulting Company and would like to know what are the basic things required to check in a baseline schedule submitted by the Contractor in order to approve it.

5 replies

Oldest first
  1. 0
    A D ·
    Best ever file compiled by anyone for reviewing schedule!!!

    http://www.ronwinterconsulting.com/rabaseline.htm

    Cheers,

    Rav
  2. 0
    Sajid Balma ·
    Excellento............ Thanks for the link.
  3. 0
    Ruel Camaquin ·
    Very Useful!
  4. 0
    Charleston-Joseph Orbe ·
    Ron Winter indeed it is brilliant.

    Do you have anything regarding reviewing a schedule during progress update

    reviewing a schedule for revise baseline.

    We do need some sort of a guidance for the above.

    Regards,

    Charlie
  5. 0
    Charleston-Joseph Orbe ·
    In addition to Ron Winter’s guidelines,

    It is also preferable to look at the contract regarding specification for planning and scheduling.

    In one of the project I was involved, there was a general specification on planning and scheduling, so in my review, i just flag what was not included as per the specification.

    The review of CPM is very important to look at the lofig in arriving at the CPM, it is really reasonable, no manipulation of logic, etc., etc.

    Regards,
    Charlie