Skip to content

Total Float for the last activity

Moutaz AldeibMember for 22 years 9 months
Created
2
1
0
Dear Planners,

I am preparing time schedule for a project, once I finished I had a look on the massive total float for all the activities, I found some activities have massive total float (activities have no successor), so I started linke those activities to another to alleviate the total float, it was good but suddenly something happened I could not understand it, the last activity in the schedule (project completion date) has got total float (it should be zero)

Could any one tell me what to do?

Regards,

Moutaz

2 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hello Moutaz,

    Try to check your "Project must finish by", in File --> Project Overview. You can remove or change it to the Finish Date of your Project.

    Regards,

    Arnold
  2. 0
    Moutaz Aldeib ·
    Dear Arnol,

    I found out the problem, another activity has got the latest date, not the project completion date.

    Thanks a lot,

    Moutaz

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?