2nd target why?
In the Open Standard
James BraghiniMember for 18 years 5 months
- Created
- 2
- 1
0
I’ve been using the early bar and creating a target bar for comparing the baseline schedule to first update. P3 manual states to create a 2nd target to evaluate against the last update. It states, "To retain historial data for each update period, rename Target 2 after each update period. An easy way to keep track of these projects is to name the project using the update period it represents. For example Target 2 projects saved during the month of April might be names 0407, 0414, 0421, 0428." I use F9 to move the date data, thus moving the early bar and leaving Target 1 as the baseline. I am confused on how to use Target 2 for evaluations and how to save. Can someone give me a simple explanation?