Dears
I have a situation here. After completing more than 50% of civil works, the Engineer issued a VO slashing the whole of the civil works from our scope.
Now, I was asked to resubmit working programme based on this VO.
My question is what would be the best way of reflecting this VO in my programme. Should I go with dissolve activities? Should I need to update the baseline also?
Please enlighten me.
I have a situation here. After completing more than 50% of civil works, the Engineer issued a VO slashing the whole of the civil works from our scope.
Now, I was asked to resubmit working programme based on this VO.
My question is what would be the best way of reflecting this VO in my programme. Should I go with dissolve activities? Should I need to update the baseline also?
Please enlighten me.
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?