Skip to content

Forecasting % Complete Using P6

Bob FodenMember for 19 years
Created
2
2
0
Dear Readers,

I’ve been asked to forecast the physical % complete of a plan at the end of the calendar year assuming all activites are proceeding to plan. Can anyone offer advise on how to do this please ?

Thanks in advance

Bob

2 replies

Oldest first
  1. 0
    Sajid Balma ·
    Tools>Update Progress; choose your date & apply
    In schedule % complete you will get the total % as if everything going exactly the way they were planned (forecast%)
  2. 0
    Bob Foden ·
    Great stuff. Thanks

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?