How do I re4strict the hour that people can work on a particular task without changing the global calendars?

2 replies

Oldest first
  1. 0
    Sue Chambers ·
    Sorry I need to know how to restrict hours on a contract without changing the global calendars in P6
  2. 0
    Ronald Winter ·
    I suggest that you copy the P6 Global Calendar and turn the copy into a Project Calendar. Then using Global Change, change all of the activity calendars from the original to the Project Calendar. Now you can change the hours in the Project Calendar as needed. Good luck!