Skip to content

Updatingn the schedule in P-3

Ali KashifMember for 18 years
Created
6
3
0

Hallo All,

Can any one guide that is it necessary to update the Hammock activities while updating a task driven schedule(To put actual dates and/or percentage complete.)

Thanks in advance.

6 replies

Oldest first
  1. 0
    Mohamed Arafat ·
    No Ali

    You do not have to update a Hammock it is updated automaticly.
  2. 0
    Ali Kashif ·

    Thank you!!
  3. 0
    Azeem Abdul ·
    Hammock is used when in an activity start and end dates are known and we want it (activity) to pick duration and adjust itself within the limits (start and end dates).

    You can find hammock activities used in Cranes and Hoists section of our programme.
  4. 0
    Ernani Garena ·
    Hello! Can anybody teach me how to create hammock activities. A sample schedule will be of great help for me to understand more hammock activities.

    You can email me thru ernan0518@gmail.com

    Thank you very much!
  5. 0
    Arnold Puy ·
    Hi Ernani,

    To create a Hammock Activity, create a new activity in their specific level and change the activity type to "hammock" then tie up with the predecessor (SS) & successor (FF).

    HTH.

    Arnold

  6. 0
    Tommy Nug ·
    For hammock activities, You have to update actual start date and actual finish date. The percentage of hammock activities shall be automatically calculated.

    Cheers,

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?