Backup / Restore Problem

Joe MansourMember for 24 years 1 month
Created
8
3
0
I am having a serious problem in the backup / restore function between one computer and all the others.
When I backup some projects, not all, from this computer, and I restore them on other computers, either it gives the message "PRBACKUP caused a General Protection Fault in module PRBACKUP.EXE at 004:7466",
or if the restore goes through, the project does not show in the list when I try the open projects.
If I click on one of the project files, P3 just starts but no response.
If I copy these projects from this computer to another one, and double click on one of the files, I receive the message "cannot open file for project XXXX".
I tried the PFXW.EXE function, it didn’t work.

I appreciate any help.

8 replies

Oldest first
  1. 0
    Anoon Iimos ·
    If you got Targets, make sure you include the targets during the back-up.

    If using pen drive, once back-up is done, try to restore it first in the same pen drive before putting it in other PCs.
  2. 0
    Joe Mansour ·
    Thanks , but It didn’t work.

    Joe
  3. 0
    Johny Kesserwany ·
    Hello Joe,



    There are several reasons why this error may occur.


    1. If restoring over an existing project, run PFXW on the existing project. But you say it didn’t work!!
    2. Restore project to another directory. If this works, then copy the project files in Explorer to the correct location.
    3. Copy the project file from the disk to a new directory on the hard drive. Restore the project from the backup copy on the hard drive.
    4. Replace the PRBACKUP.EXE file using Setup Utility.
    5. Open Task manager (Ctrl-Alt-Del) and check for possible conflicting programs. Close any programs not in use and unload all programs not in use.


    Hopefuly it could help.



    Regards

    JK


    http://www.linkedin.com/in/johnykesserwany

  4. 0
    Ronald Winter ·
    P3 cannot address schedules that are deeply buried in your directory structure. Make sure that the new computer does not store your schedules with a full path name greater than 64 characters (including file name.) If so, move them higher. Good luck!
  5. 0
    Joe Mansour ·
    Thanks Ronald and Johny,

    Johny, I tried your suggestions, none worked.

    Ron, the project I am trying to restore is in the P3WIN/PROJECTS directory.

    I was told by our IT people that there could have been a conflict between P3 and some program I installed; but since I reisntalled P3, it seems that a Windows file that P3 uses could have been damaged, but there is no way of finding which file it is. The only solution they are suggesting is to format the computer; I am trying to avoid this surgical intervention.

    Can you come up with other ideas?

    Regards,

    Joe
  6. 0
    Ferdinand Fincalero, PMP ·
    Hi Joe,

    Before moving on to the ultimate solution for the computer problems by formatting, try treating your system first with the latest available anti-virus. Somehow, it may help and solve your problem.

    Cheers!
  7. 0
    Joe Mansour ·
    Thank you.

    My computer is continuously updated with the latest anti-virus. I am quite sure the problem is not emanating from a virus.
  8. 0
    José Reis ·
    Hi Joe!

    You said that do a backup. Can you said how you do this backup? Is a export? XML, XER or other? How Export Type? Projet; Resource Only or Role Only? How many projets in the same time? And for which drive?