Early Start vs. Actual Start in P3.1

Ruel CamaquinMember for 17 years 11 months
Created
4
2
0
Guys,

Just like to know why is the EARLY START dates also changes to the actual start dates everytime i encode the ACTUAL START date? Is there a trick or method to make the EARLY dates fixed to the target dates. Thanks in advance for the early response.

Cheers & Regard.

4 replies

Oldest first
  1. 0
    Anoon Iimos ·
    make a target, so that it become fixed.
  2. 0
    Ruel Camaquin ·
    I aleady have a target schedule. The only thing is that everytime i encode the actual start and finish dates, the early start column dates also changes to the actual dates i encoded. Ex. masonry works early start is 10NOV08 as the target, then i encoded 15NOV08 as an actual start for masonry works - after i clicked the ok button, the early start date for the target also changes to the actual start date of 15NOV08A although the bar chart does not move.

    I cannot compare the early start and the actual start with just the bar charts alone, i need to have the early start dates same as the target reference against the actual start.
  3. 0
    Ferdinand U. ·
    add target1 early start and target1 early finish column
  4. 0
    Ruel Camaquin ·
    It is a very big help! i’ve even added variance column, now i can see me delays and ahead in my schedule.

    Thank you so much.