Actual % Completion vs. Planned % Completion

Basel Al-JazzarMember for 23 years 1 month
Created
8
3
0
how an i disconnect the actual % completion for each activity from the actual duration - in other way, to feed the % completion manually and not to be related the actual duration of the activity ? and how can i show the planned % completion for each activity linked with the planned early start of each activity ?

8 replies

Oldest first
  1. 0
    Santhosh kumar Narayanan ·
    for actual progress u will be puting manually right? for planned % progrss make a copy of ur target auot up date that u and see % complete. to auto update go to tools, update progress, (Check for all activity)
  2. 0
    Ronald Winter ·
    This is Autocost Rule #1. Select Tools / Options / Autocost Rules. The Un-check the first rule, "Link remaining duration and scheudle percent complete." Good luck!
  3. 0
    Basel Al-Jazzar ·
    thanx for reply, when u uncheck the first time this will lead that i have to fee actual % completion manually. But what about target % completion ? shall i feed it manually then ??
  4. 0
    Mohamed Basheer ·
    Mr. Basel

    Planned Progress will come only if you have a Target assigned and Update the target programme through update progress as on data date.( No manual work)

    Hope i am right.

    Regards
    Yembee
  5. 0
    Ulysses Garcia ·
    Hi

    Target % will only show if you copy your schedule as target then compare it to the current schedule update as of D.D.( data date).. Menu..Tools > look for target in sub menu...
  6. 0
    Edgar Ariete ·
    i guess nobody is planning to be late! just in case, make all your activities critical (in target project), that means zero total float for all the activities! and update it..

    i hope it works
  7. 0
    Edgar Ariete ·
    Hassan,

    You can make as many target project as you like, but actuals are actuals. You can never have two actual start or actual finish for the same activity at the same time.

    Updating Target is realizing your plan. Modeling it as if it actually happened.

    Then compare it with your current project (which is your actual one), a dynamic project that reflects your actual resources and performance.

    hope this explains my view...
  8. 0
    Edgar Ariete ·
    Hassan,

    Yes you can. If you planned it late. Just make two (2) targets. One early target and one late target (just make sure you can get approval for your late target).

    this is free anyway...