Skip to content

Progress Highlights

Ruel CamaquinMember for 17 years 11 months
Created
2
3
0
Is there a way that i could filter Progress highlights on the scheduled works (target/baseline) or summarized project by certain time period?

It is like that i wanted to inform my project time which works should be starting or finished on a certain period of the project or the works highlighted by progress hightlight. Thanks in advance for the quick replies.

Cheers!

2 replies

Oldest first
  1. 0
    Ferdinand Fincalero, PMP ·
    Hi Ruel,

    There is no such facility of filtering activities using progress spotlight in primavera. Utilizing the progress spotlight gives you an ease in updating your program and in taking a look at the current activities of your project as by default it always starts in the data date.

    For information dissemination to your project superiors on the current status of your project schedule, why not use a two-week lookahead or a one-month lookahead presentation. They would appreciate it more.

    In Service,
    Ferdinand
  2. 0
    Ruel Camaquin ·
    Great response, i’ll follow your advice.

    Again Thanks & Cheers!

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?