Bars and Baselines in P6

James BraghiniMember for 18 years 5 months
Created
1
1
0
How can I get the bars for both Primary and Secondary Baselines to come up on Gant Chart? Also, I was wanting to have the Predessor be on the Primary and the Successot to should on the Secondary.

Can someone give a quick lesson on this?

Thanks,
James Braghini

1 reply

Oldest first
  1. 0
    Arnold Puy ·
    Hi James,

    You can do this by Formatting your Bars. Before doing this make sure that you have assigned both for primary & secondary baseline.

    Afterwards, Go to View -> Bars -> mark the box next to "Primary & Secondary" under the bar style tab you change the shape, color, pattern & row. Under the bar labels tab, select the "primary" & select add underneath & select label as predecessor. Do the same way with the secondary.

    HTH.

    Regards,

    Arnold