Hello,

I’m working with Primavera P3.
I will synchronise my schedule with a database (Roser) to export my primavera database.
Before I will run several query’s with MS Acces to synchronise the both databases I must export a batch with Tools --> Tabular report --> Productions --> Run series.

Now is my question ;

Can I synchronise the database of P3 with MS Acces directly en without running the batch (Tools --> Tabular report --> Productions --> Run series.), because it takes a long time to run the batch.

I hope you can help me with the problem.

Kind regards,

Arjan Leijten

2 replies

Oldest first
  1. 0
    David Kelly ·
    The short answer is yes.

    BUT you need to use the btrievs ODBC drivers. This is NOT for the feint-hearted.

    They may no longer work on XP, I do not know.
  2. 0
    Gün Göksu ·
    they work on XP.
    and nope. definitely NOT for the fainthearted. :)