export resource usage spread sheet in p5

Mubashir waniMember for 19 years 5 months
Created
8
1
0
Can anybody help me to know how can we export resource usage spread sheet in p5

8 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Mubashir
    You’ll create a report with "Time Distributed Data" marked from the group Resource Assignments (or a similiar name). Then you’ll be guided by the wizzard. As output format you’ll select text/ASCII-file.
    Regards
    Dieter
  2. 0
    Mubashir wani ·
    Dieter Wambach

    Thanks for your reply, you are right but i guess in P5 we can not export "Resource Usage Spread sheet" in excel format. Where as in P3 we can get such outputs in formats like csv or wk1.There it used to help me in production of S-Curves with lot of flexibility.
    Please Comment
  3. 0
    Dieter Wambach ·
    Mubashir
    P3 and P5/P6 are different programs, not just two different versions of the same one. So, many algorithms and procedures are different.
    The way to produce and then save a report for export to EXCEL is rather easy. The produced format is csv and you can set a parameter that Excel automatically opens after the data was produced - the report ran. We produce most of our s-curves this way - just run the report. I don’t miss the P3 ability.
    Just try it.
    Regards
    Dieter
  4. 0
    Mubashir wani ·
    i still unable to do it, one more query sir: how to print resource usage profile??
  5. 0
    Dieter Wambach ·
    Mubashir
    reporting in P5 is very easy. Try it.
    Print resource usage profile:
    View "Activities" --> "resource usage profile" --> File --> "Print Preview" --> "Page Set-up (The Icon upper left corner) --> walk through the detail tabs --> "Options" mark "Resource Usage Profile"
    Regards
    Dieter
  6. 0
    Alex Wong ·
    Mubashir

    I try to give you a step by step guide. HTH

    1. Open Your project

    2. Then Click assignment

    3. Change Timescale @ the spreadsheet to month or week

    4. Highlight the activity

    5. Click Ctrl C

    6. Open Excel

    7. Click Ctrl V

    That should work

    ALex
  7. 0
    Mubashir wani ·
    I am really thankful to both of you.
    I am able to do it now.
    Thank you once again
  8. 0
    Ameen Pasha ·
    can u do the favour the same to me,...

    with regards,

    Mr. Ameen N Pasha,
    ameen_pasha10@yahoo.com

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?