Leveling gap’s

Arjan LeijtenMember for 17 years 10 months
Created
6
3
0
I have a problem with a gap on the end of the working day.

For example ;

Contractor "A" is finished at three o’clock en the workday ends on four o’clock.
The next contractor "B" will not line up his manpower for 1 hour en start next day in the morning, because that is not efficient. I have 1 hour not used practicly, but in my planning contractor "B" started on three.

How can I make a maximum resource leveling about
the lost hour in the day before (from three till four)

Kind regards,

TRN (Total Raffinaderij Nederland)

Arjan Leijten
Scheduling engineer



6 replies

Oldest first
  1. 0
    Arjan Leijten ·
    Is there no one who can help me........

    Arjan Leijten
  2. 0
    Ferdinand Fincalero, PMP ·
    Dear Arjan,

    If you are using P3 it is not possible as its lowest count of duration is in days. But if you are using the latest versions of P5 or P6 you can always customize the resource shift and calendars to suit your program in hours. You can find it in menu>enterprise>Calendars or >Resource shifts. Since you are dealing with two different contractors, I suggest that you may assign different calendar settings for each of them with detailed working hours.

    May I further advice to check suitability of your resource limits and leveling settings to avoid gaps after leveling.

    Hope this is of help to you.
  3. 0
    Ferdinand Fincalero, PMP ·
    Dear Arjan,

    If you are using P3 it is not possible as its lowest count of duration is in days. But if you are using the latest versions of P5 or P6 you can always customize the resource shift and calendars to suit your program in hours. You can find it in menu>enterprise>Calendars or >Resource shifts. Since you are dealing with two different contractors, I suggest that you may assign different calendar settings for each of them with detailed working hours.

    May I further advice to check suitability of your resource limits and leveling settings to avoid gaps after leveling.

    Hope this is of help to you.
  4. 0
    Arjan Leijten ·
    Ferdinand,

    I,m sorry, but the lowest value in P3 is in hours. Standard is days but in "project overview" you can change days in hours........

    Arjan Leijten

  5. 0
    Ferdinand Fincalero, PMP ·
    Yes that’s right Arjan, I just seem to be not using hours in P3 for a long time with the projects that I am dealing with and especially now that there is an alternative programs of P5 & P6. I stand corrected.

    Well then, I guess you already know the different ideas in overcoming that gap in your program with the different functions such as in leveling priority, splitting, relationships, constraints, limits, calendars, etc... What I usually do when I encounter some operational difficulty in making things right in my schedule is that I keep on experimenting on the case until I get it right or until I retire with the question on my head. That’s then the time that I will come out to ask the others. But so far, I haven’t done so in PP, and thanks God that I always was able to work out things right, and I feel it more fulfilling.

    Won’t there be any compliment for responding rather than be commented? I hope that somehow I was of help to you.

    In Friendship,
    Ferdinand
  6. 0
    Arjan Leijten ·
    OK. Thanks !!

    Arjan Leijten

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?