Leveling gap’s
In the Open Standard
Arjan LeijtenMember for 17 years 10 months
- Created
- 6
- 3
0
I have a problem with a gap on the end of the working day.
For example ;
Contractor "A" is finished at three o’clock en the workday ends on four o’clock.
The next contractor "B" will not line up his manpower for 1 hour en start next day in the morning, because that is not efficient. I have 1 hour not used practicly, but in my planning contractor "B" started on three.
How can I make a maximum resource leveling about
the lost hour in the day before (from three till four)
Kind regards,
TRN (Total Raffinaderij Nederland)
Arjan Leijten
Scheduling engineer
For example ;
Contractor "A" is finished at three o’clock en the workday ends on four o’clock.
The next contractor "B" will not line up his manpower for 1 hour en start next day in the morning, because that is not efficient. I have 1 hour not used practicly, but in my planning contractor "B" started on three.
How can I make a maximum resource leveling about
the lost hour in the day before (from three till four)
Kind regards,
TRN (Total Raffinaderij Nederland)
Arjan Leijten
Scheduling engineer
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?