Leveling

Harzelli BouasriaMember for 18 years
Created
6
3
0
Hi All
when I level resources, primavera spots there for later dates, or the resources are available.
why primavera do this?
to solve this problem I will always forcing the tasks.
is anyone have a solution for this problem?.
Thanks

6 replies

Oldest first
  1. 0
    Mimoune Djouallah ·

    hi;

    perhaps you have reached the maximum level of your resources ( in resources dictionary, normal, max)

    not sure, as leveling is a kind of black magic for me ;)


    mimoune

    on doit se voir khou ;)
  2. 0
    Harzelli Bouasria ·
    Salam mimoune
    is not a resource max problem, it shifts there to far after 2 months, but the resources are available well before.

    je ss d’accord il faut qu’on se voit khou :)
  3. 0
    Rafael Davila ·
    harzelli

    My first thought would be that you are using some of the smoothing options under Tools/Level/Smoothing, if so try selecting smoothing-none and reschedule/level.

    Best regards
    Rafael
  4. 0
    Harzelli Bouasria ·
    Hi Rafael
    it’s work with Time constrained
    thanks a lot my friend
  5. 0
    Rafael Davila ·
    harzelli

    You’re welcome.

    Best regards,
    Rafael
  6. 0
    Alexandre Faulx-Briole ·
    Harzelli,
    you should print and review the help page about levelling; it is rather sophisticated, but very usefull if you want to understand how to use resource levelling in P3
    do you still have difficulties when levelling resources on the "drawing" tasks in the project?
    I hope everything is going well for you in Arzew, have a good month of ramadhan by the way
    Alexandre
    P.S. Same for you, mimoune kho