Planners,


Anybody have encountered this problem in updating, I have an activity to update resourced and cost loaded , I have inputted the actual start but when I input the % complete it does not accept the data I input it goes back to 0%.

Thank You

Pacifico

3 replies

Oldest first
  1. 0
    Jan Richard Noble ·
    Hi Pacifico,

    Try to copy the file and work with the copied one. it might be corrupted...

    regards,

    jan
  2. 0
    Pacifico Pallasigui ·

    I have solved it in the resource tab I uncheck the driving of all the resources and the % appeared ..Can anybody know whats the reason for this??
  3. 0
    osama Eltantawy ·
    when the resource is a driving resource P3 calculate the percent complete based on resource % complete rather than activity % complete. so, you have to make the resource is not driving and update the activity % complete OR update the driving resource % complete and it will be reflected on the activity % complete.

    Osama,

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?