% Complete Updating Problem
In the Open Standard
Pacifico PallasiguiMember for 22 years 8 months
- Created
- 3
- 3
0
Planners,
Anybody have encountered this problem in updating, I have an activity to update resourced and cost loaded , I have inputted the actual start but when I input the % complete it does not accept the data I input it goes back to 0%.
Thank You
Pacifico
Anybody have encountered this problem in updating, I have an activity to update resourced and cost loaded , I have inputted the actual start but when I input the % complete it does not accept the data I input it goes back to 0%.
Thank You
Pacifico
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?