Updating the schedule in P3
In the Open Standard
FT
Fernando TubiaoMember for 17 years
- Created
- 10
- 3
0
Hello, I would like to know how the schedule update process is done in P3. I have the following questions:
1. What fields / columns do you update when you do your schedule update in P3?
2. Do you do your changes (of those fields / columns) in P3 BEFORE running the scheduling option (F9) or AFTER?
3. Do you move / shift your data date BEFORE running the scheduling option (F9) or AFTER?
Thanks in advance.
1. What fields / columns do you update when you do your schedule update in P3?
2. Do you do your changes (of those fields / columns) in P3 BEFORE running the scheduling option (F9) or AFTER?
3. Do you move / shift your data date BEFORE running the scheduling option (F9) or AFTER?
Thanks in advance.
10 replies
Oldest first- 0SHShah. HB ·1. you need to plug in actual dates,percentage in activity column and press f9
2.If you use tools update progress you don’t have to plug in anything since it is used to show planned percentage
3.changes to data should be done before scheduling
4.Data date shifts according to scheduling dates u mention in the scheduling option - 0FTFernando Tubiao ·Hi Shahul, thanks for your answer. Now, does this % Comp (percentage) field have to do anything with the progress you do separately? (i.e. in construction each activity is typically given a weighting based on manpower or cost, and percentage complete is physically measured / estimated on site).
- 0RDRafael Davila ·Fernando,
If you have linked %complete and remaining duration then whenever you edit one the other is recomputed according to the following formulas.
If you enter %complete remaining duration will be recomputed as follows:
REMAINING = ORIGINAL (1 - %COMPLETE) when there is no actual, otherwise
REMAINING = (ACTUAL/%COMPLETE) – ACTUAL
If you enter remaining duration %complete will be recomputed as follows:
%COMPLETE = 1 – REMAINING/ORIGINAL when there is no actual, otherwise
%COMPLETE = ACTUAL / (ACTUAL + REMAINING)
This method might create confusion, especially after you have actuals from previous updates. Let say you have an activity with original duration of 2 weeks but after 2 weeks is 50% done and you expect to finish the remaining 50% in one week for a total duration of 3 weeks. If you enter these values into the above formulas you will get:
REMAINING = 2 /.5 – 2 = 4 – 2 = 2 weeks
%COMPLETE = 2 / (2+1) = 2/3 = 0.667= 66.67%
This mean you should have entered 66.67% to get 1 week for remaining duration.
REMAINING = 2 / 0.6667 – 2 = 3 – 2 = 1 week
The automatic linking of the two is one of the most common pitfalls of scheduling software programs. Cost loaded schedules are particularly susceptible to this scheduling pitfall, because the percent complete is tied to the earned value and cost to complete for each activity. Thus the percent complete must be accurately reported otherwise the cost reports will be inaccurate.
You have two options:
1. Keep the formula link and in the activity details enter either and the software will recalculate the other as per your last entry. Here formulas might confuse you.
2. Unlink the formulas and set each individually. Keep it simple and avoid any pitfall.
My recommendation is go with option 2, and then ask at the site, what is the remaining duration in work days after the update data date. You will enter remaining durations for your activity duration computations and no change in %complete will be done at this point. You will enter %complete for your cost and EV computations and no change in remaining duration will be done at this point.
KEEP THEM SEPARATE.
Best regards,
Rafael - 0FTFernando Tubiao ·Thanks Rafael for your answer. My understanding is that the schedule is used for DATES, not for PROGRESS (you plan and control the time of your project, i.e. from the schedule you are able to know your mechanical completion date).
Having said that, I have two more questions:
1. Shouldn’t you just update your Actual Date and / or Remanind Duration fields / columns everytime you update your schedule (i.e. on a bi-weekly basis)?
2. Why do you need to update the %Comp (percentage) field / column in P3 if your progress report is being done separately in Excel? Or, do you use the %Comp field / column in P3 for physical progress reporting purposes? - 0RDRafael Davila ·Fernando:
The very basic updating procedure is to update Actual Start, Actual Finish and %complete/(or remaining duration). I recommend use Actual Start/Actual Finish/Remaining Duration.
For all started but unfinished activities during the update period make sure you have the appropriate remaining duration as it will not necessarily be adjusted automatically.
Remaining duration is measured from Data Date unless you have out-of-sequence progress selected Retained Logic for out-of-sequence progress instead of Progress Override. The selection is an issue per-se for a long debate.
For reasons beyond my comprehension the default set by primavera for %complete and remaining duration is that these are linked, that is one is the function of the other, but this is not always the case, to me keeping them linked does not make sense. Therefore you got to go to the options screen and make the appropriate selection.
You can enter the data from several screens, is your choice. You can also use Primavera Mail utility to make your updates but again for reasons beyond my comprehension the default setting by primavera is to update using %complete.
Also %complete is used to update other fields depending on your settings. Because I no longer use P3 and do not have a license installed in my computer I cannot tell you specifically which options you have.
If your job is resource and cost loaded, then as part of your regular updating you have to update actuals for resource usage and costs. With regard to costs in order to get true time/cost distributions you got to follow a procedure to update actuals, is irreversible in P3. Here P3 is the worst of all software.
Best regards,
Rafael - 0RDRafael Davila ·Shahul,
Scheduling is used for planning not only your dates but also your resources.
Seems like Fernando is starting with the logical thing first, time. When CPM started in the 50’s it was just abouut time, then more functionality was added and still today many don’t realize how they are related. I have clients who do not resource load their jobs, unbelievable but true. How can you make a job without accounting for resources?
Eventually Fernando will get into the other things,very soon, the same way we are frequently helped by others, those of us willing to assit him will be here, Planning Planet is a two way street.
Best regards,
Rafael
- 0FTFernando Tubiao ·Thanks Rafael and Shahul for your inputs. When I said that my understanding was that the schedule is mainly used for dates and not progress, I meant that there’s no need to update the %Comp field in P3; you just need to update Actual Start/Finish and/or Remaining Duration. Physical progress is updated separately, usually in an Excel spreadsheet. I think Rafael is right when he says that the schedule is also used for resource planning.