Report to show actual vs target W/O resources

Jason AudetteMember for 18 years 4 months
Created
2
1
0
All,

I am trying to produce a report that shows actual vs target %complete. My schedules are NOT resource loaded. How do I show, in a graph, that either we are on schedule, behind or ahead? I know I cannot produce a S-curve without resources. It was mentioned to set up resource called time and use the durations as amounts but I am unclear on how to do that. Any help would be great.

2 replies

Oldest first
  1. 0
    Mimoune Djouallah ·
    hi

    just assign a resource to all activities " let’s call it TIME for simplification" with 1 as units per day, then you can generate your S curve

    HTH
  2. 0
    A D ·
    define a resource and then put BQ=OD using global change

    and then plot the graph