As-Built Schedule
In the Open Standard
Adekunle ArisilejoyeMember for 18 years 6 months
- Created
- 10
- 1
0
How do you build this into your schedule.
Actual Start Mar 05-Mar 06, Work suspend Mar 7- Mar 9, work resumes Mar 10 -12, Work Suspends Mar 13-15, Work resumes MAr 16 to finish on 18.
The work suspension is perculiar only to this task. Othr tasks are going on as normal.
Cheers
Actual Start Mar 05-Mar 06, Work suspend Mar 7- Mar 9, work resumes Mar 10 -12, Work Suspends Mar 13-15, Work resumes MAr 16 to finish on 18.
The work suspension is perculiar only to this task. Othr tasks are going on as normal.
Cheers