As-Built Schedule

Adekunle ArisilejoyeMember for 18 years 6 months
Created
10
1
0
How do you build this into your schedule.

Actual Start Mar 05-Mar 06, Work suspend Mar 7- Mar 9, work resumes Mar 10 -12, Work Suspends Mar 13-15, Work resumes MAr 16 to finish on 18.

The work suspension is perculiar only to this task. Othr tasks are going on as normal.

Cheers

10 replies

Oldest first
  1. 0
    Safak Vural ·
    Dear Bobo,

    Please check the Dates tab and you can find the suspend and release options. YOu can add more than one suspensions to your activity.

    Regards,

    Safak
  2. 0
    Adekunle Arisilejoye ·
    Exactly wat I tot. but how do ou do dt. Meanwhile I will try and figure it out.

    Cheers
  3. 0
    Safak Vural ·
    You can find at

    view-activity detail-dates

    regards,

    Safak
  4. 0
    Adekunle Arisilejoye ·
    Safak,

    Yes I know that but how do you build in multiple suspensions. Pls explain

    Cheers
  5. 0
    James Shimmon ·
    Bobo
    I’m not sure about multiple suspensions and whether it is possible - you could create a calendar that has the suspend dates as non-working time
    Cheers

    Shimmo
  6. 0
    Adekunle Arisilejoye ·
    the calendar option cant work. cos Im talking about 1000 activities and there are several task with such breaks but at differnt dates. Do I have to create calendars for each tasks.

    Cheers
  7. 0
    James Shimmon ·
    yeah you would
  8. 0
    Safak Vural ·
    Dear Bobo,

    If you create and update as-built programme weekly (monthly if weekly information does not exist), then you can create multiple suspensions with using store period performance. The important point is that you will not need the suspension at all. Do not give any % in given period and remark the suspension dates in log and put in any view you want to use in your CLAIM (I think the reason for the study is that). The other important point that you need to update your programme at least monthly while importing old data. The reason is htah if you not the resources will be evenly distributed (depends on resource curve) along all of the duration.

    Regards,

    Safak
  9. 0
    Safak Vural ·
    Dear Planner,

    If you suspend, there will be neck. If you make this days as holidays in a calendar. This also become a neck. But I recommend suspend. It also provide you to give a log about it. You can use attachment tools to attach shapes, notes to the bar chart view for your presentations.

    Regards,

    Safak
  10. 0
    Safak Vural ·
    The only way is do not progress the activities and put it with attachment tools as objects. You can hatch a period of time with just one click. View--Attachment Tools. You can use PRMDRAW.EXE in the P3 directory to create many different objects or edit photos etc.

    Regards,

    Safak