Weighting Factor for computing % complete

Lalith RathnayakeMember for 18 years 1 month
Created
2
1
0
Dear Planners,

I am using P3 (ver.3.1)

- My program is resource loaded for Labor, Material and equipments with Cost Category values L, M, & E respectively.

- I want to use Manhours ( i.e. only labor resources) as weighting factor when computing % complete.

- When I select resource units as weighting factor (Tools --Option -- summerization -- resource units) P3 uses all resources regardless of the unit.

- How can I use only Labor resources as weighting factor for computing % complete

- Is it not advisable to load all resource categories to the schedule in this case ?

Please advice. Thank you in advance

Lalith

2 replies

Oldest first
  1. 0
    Tabeeb Ur Rahman ·
    define a filter, cnditional to manpower
  2. 0
    Lalith Rathnayake ·
    Dear Thabeer,

    Can you explain further ?

    As I undrstood, even if you apply a filter P3 still sum up all resources (regardless of their unit) to compute budgeted quantity.

    What I need is to get only the sum of manhours in the Budgeted quantity field.

    Do i need to remove the other resource assignments (i.e. Material and Equipments) to achieve this ?

    Please advice.

    Lalith

Log in or join to reply