Weighting Factor for computing % complete
In the Open Standard
Lalith RathnayakeMember for 18 years 1 month
- Created
- 2
- 1
0
Dear Planners,
I am using P3 (ver.3.1)
- My program is resource loaded for Labor, Material and equipments with Cost Category values L, M, & E respectively.
- I want to use Manhours ( i.e. only labor resources) as weighting factor when computing % complete.
- When I select resource units as weighting factor (Tools --Option -- summerization -- resource units) P3 uses all resources regardless of the unit.
- How can I use only Labor resources as weighting factor for computing % complete
- Is it not advisable to load all resource categories to the schedule in this case ?
Please advice. Thank you in advance
Lalith
I am using P3 (ver.3.1)
- My program is resource loaded for Labor, Material and equipments with Cost Category values L, M, & E respectively.
- I want to use Manhours ( i.e. only labor resources) as weighting factor when computing % complete.
- When I select resource units as weighting factor (Tools --Option -- summerization -- resource units) P3 uses all resources regardless of the unit.
- How can I use only Labor resources as weighting factor for computing % complete
- Is it not advisable to load all resource categories to the schedule in this case ?
Please advice. Thank you in advance
Lalith
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?