Quantifying Percent delay into number of days
In the Open Standard
Chandan KakatiMember for 18 years 5 months
- Created
- 5
- 3
0
Hi all,
Can somebody tell me whether there is any way to quantify % delay to number of days of delay. I have a delay in 0.79% in percent complete. Now the client want me to tell them in terms of days. The project duration is around 400 days and the critical path activities are not delayed.
cheers!
Chandan
Can somebody tell me whether there is any way to quantify % delay to number of days of delay. I have a delay in 0.79% in percent complete. Now the client want me to tell them in terms of days. The project duration is around 400 days and the critical path activities are not delayed.
cheers!
Chandan
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?