Sort by Cost Accounts

A DMember for 19 years 5 months
Created
1
2
0
Hi,

For a project ABC, we have created 26 cost accounts from A to Z.

Now, is there any way we can sort the cost accounts in ascending or descending order?

What i have tried is, i have created a CDI called COST and then using Global Change i hav done BC = COST

Opened the OPTIONS window and then grouped by cost accounts and then sort by COST.

What it does is, sort the activities within that cost account but not for the project.

In simple terms, lets says,

Value of Cost Account A = 12,784,000/-
Value of Cost Account B = 15,783,476/- and
Value of Cost Account C = 14,265,789/-

Now, my question is, is there any way we can have these cost accounts in descending order i.e. in order of B, C and A

Plz advise

:-)

1 reply

Oldest first
  1. 0
    Mimoune Djouallah ·
    not sure what you want to do, but have you tried resource profile/table then select by cost account !!!!